Loading...
Loading...
Loading...

Progress being made in new harbour project | THE DAILY HERALD

May 21, 2021

Progress being made  in new harbour project | THE DAILY HERALD
Loading...

The Black Rocks area where Saba’s new harbour is slated to be built.

SABA--The project to construct a new harbour at Black Rocks is proceeding.

Loading...

  The existing dirt road has been widened and rock catchment benches have been created to provide safe access to the Black Rocks area.

  The intention is to start construction of a grouted rock wall along the road soon and to initiate preparatory works for utilities. Various studies have been completed that provide important information for the further elaboration of this comprehensive project, financed by the Dutch government.

  The archaeological site survey by Saba Archaeological Foundation SABARC has been concluded. Several artefacts were found in the Black Rocks area, including two old ship cannons that will be moved to a dive site. The soil investigation and the laboratory tests of the soil samples taken from the land and seabed are finished. The fieldwork by a team from Geotron of the Netherlands was concluded in September last year, after which laboratory tests were done on the soil samples.

  The outcome of the soil investigation helps to determine what construction methods are feasible for the breakwater. One possible method, a cofferdam breakwater, requires driving of piles. The soil investigation shows that this could be a challenge at the Black Rocks location, because of some large boulders situated in the deeper layers of the seabed. A specialised company has been asked to advise on this aspect.

  Through physical model tests at University of Ghent, Belgium, the strength of different construction methods was tested. For this purpose, two scale models, a vertical (caisson/cofferdam) and a berm (rock) breakwater were exposed to different wave conditions, up to those of a category five hurricane.

  These test results will serve as input for the general design of the harbour by Witteveen+Bos of the Netherlands and for the marina design by ATM Design Engineering Consulting of the United States. Harbour project manager Ton van der Plas explained that even though the physical model tests showed that the wave forces of a category five hurricane were five times lower at Black Rocks than at Fort Bay, the wave impact is still very heavy.

  An environmental impact assessment (EIA) was carried out by Ecovision of Curaçao as part of the permit application. The extensive report is ready in draft format, but still needs to be discussed with the stakeholders.

  The assessment addresses the environmental impact of the harbour development on both the landside and marine life. Focal points include the colonies of elkhorn coral (Acropora palmata) in the project area, which is a protected species. These coral colonies will have to be relocated before the harbour construction starts.

  Saba Conservation Foundation (SCF) is running a pilot project to determine the best relocation method and location. Fragments of four coral species were moved to two different locations. So far, monitoring of the fragments has shown that the best location to replant the corals is “Hole in the Corner”, east of Black Rocks.

  The EIA also points out that the cliffs of St. Johns, close to the harbour development, are a nesting site for the protected red-billed tropicbird (Phaethon aethereus). Measures must be taken to avoid disturbing these birds during the construction of the harbour.

  Another important topic in the EIA is the risk of erosion, which has a negative impact on the corals. The proposed new harbour will be constructed in a zone that is already affected by uncontrolled erosion, largely caused by roaming goats. Development of the area will further impact the still-vegetated land. This aspect must be tackled through the goat control project and revegetation of the area.

  The EIA concluded that a major project such as a harbour development is bound to have an adverse impact on nature. The objective is to keep this adverse impact on the environment to a minimum and to balance it in the decision-taking process with the economic, social and safety impacts.

  Van der Plas presented all these latest developments to the Island Council on May 6. According to Van der Plas, there was a lot of interest and many questions were asked.

  For the next few months, the project will focus on the detailed design, the permit application and the tendering procedure. Tendering for new harbour is scheduled to start before the end of this year.

https://www.thedailyherald.sx/islands/progress-being-made-in-new-harbour-project

Source: https://www.thedailyherald.sx/islands/progress-being-made-in-new-harbour-project

Loading...

Headlines

Armed and dangerous suspect remains wanted in “Alligator” double-murder investigation

August 22, 2026

Armed and dangerous suspect remains wanted in “Alligator” double-murder investigation

The Police Force of Sint Maarten (KPSM) and the Prosecutor’s Office are renewing their appeal for information concerning the suspected shooter in the ongoing “Alligator” investigation. The suspect remains at large and is considered armed and dangerous.

August 19, 2026

Court convicts two defendants in “Jasmine” investigation | Soualiganewsday

SINT MAARTEN (GREAT BAY) - The Court of First Instance has rendered its judgment in the criminal cases against M.R. and J.E.B., the remaining defendants in the “Jasmine” investigation. Both defendants were convicted of co-perpetrating fraud and money laundering. M.R. was also...

August 19, 2026

Approx. $53 million budgeted for new Pointe Blanche Prison | The Daily Herald

Artist’s impression PHILIPSBURG--Construction of the new Pointe Blanche prison began in January 2026 and is expected to be completed by July 2028, according to Minister of Justice Nathalie Tackling. The project is being implemented through the United Nations Office for Project...

Loading...
Loading...
Loading...