Reconstruction work to start at PJIA Nov. 16 | THE DAILY HERALD

November 12, 2020

Reconstruction work to start at PJIA Nov. 16 | THE DAILY HERALD
Loading...

PHILIPSBURG--After finalising the design and planning phase, the specialised mould clean-up and waste disposal pre-work will start at Princess Juliana International Airport (PJIA) on November 16, 2020.

  On Monday, November 9, PJIAE’s project reconstruction team held an important kick-off meeting together with the main contractor AAR Inc. and St. Maarten based sub-contractors Tidal Wave and All Caribbean. During the meeting, it was concluded that the mould remediation, surface decontamination and waste disposal works at the Airport’s former check-in hall will officially start on Monday, November 16. It is envisaged that the pre-works will be completed in April 2021, followed by the reconstruction of the Terminal Building. The pre-works include the degutting of the interior of the building and removal of all contaminated materials that are not reusable anymore.

Loading...

  “It is expected to be a very successful project and I’m happy to see the turn out of the kick-off meeting for the mould remediation and waste disposal works. I’m also elated to witness the collaboration from the St. Maarten based local subcontractor Tidal Wave, as they are prepared to provide the massive workforce, and of All Caribbean, which will be executing the Waste Disposal for this major undertaking,” said PJIAEs Project Director Mirto Breell.

  The oversight and supervision of the remediation works, including sampling and testing of the completed work areas will be conducted by Farmer Environmental Group, a partner of PJIAE, that did the initial remediation work back in 2018, for the current operational floor space.

  To keep workers, PJIAE staff and the Airport community safe, PJIAE’s Project Coordinator Damien Schmidt will conduct an extensive training session on the COVID-19 safety measures and the airport construction safety procedures.

  The year 2021 is an important one for PJIAE with the awarding of the terminal reconstruction contract. This will mark the start of the construction phase planned for May 2021. The invitation for this tender was published last month (October 26, 2020).

  For more information on this go to www.sxmairport.com and search under construction, Project - Package 2 - Reconstruction of the Terminal Building (P2.)

https://www.thedailyherald.sx/islands/reconstruction-work-to-start-at-pjia-nov-16

Source: https://www.thedailyherald.sx/islands/reconstruction-work-to-start-at-pjia-nov-16

Loading...

Headlines

Contour Airlines announces new nonstop service between St. Thomas and St. Maarten | The Peoples Tribune

July 23, 2026

Contour Airlines announces new nonstop service between St. Thomas and St. Maarten | The Peoples Tribune

SXM AIRPORT--Contour Airlines today announced new nonstop service connecting two of the Caribbean's most iconic destinations: St. Thomas, U.S. Virgin Islands, and St. Maarten. The new route will operate between Cyril E. King Airport (STT) and Princess Juliana International Air...

July 22, 2026

GEBE given until July 27 to justify fuel-clause increase for BTP review | The Daily Herald

Head of BTP. Judianne Labega-Hoeve during meeting with Minister of TEATT, Grisha Heyliger-Marten, TEATT Chief of Staff, Otmar Jonis and Legal Council to the Minister of TEATT, Joeri Essed. POND ISLAND--The Bureau Telecommunication and Post (BTP) has given utilities company NV...

July 21, 2026

Scooter rider was arrested Monday morning with firearm | Soualiganewsday

SINT MAARTEN (GREAT BAY) - On July 20th, at approximately 9:50 p.m., officers of the Korps Politie Sint Maarten (KPSM) Patrol Unit were conducting a routine patrol when they observed an individual riding a scooter. Officers attempted to stop the rider for a control;...

Loading...
Loading...
Loading...